France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

France orders first long-lead items for PA-NG carrier

by Kate Tringham

An artist's impression of the French Navy's PA-NG next-generation carrier. (MO Porte Avions)

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first order for long-lead items for the country's future Porte-Avions Nouvelle Génération (PA-NG) next-generation nuclear-powered aircraft carrier (CVN), the French Ministry of the Armed Forces has confirmed.

In a 30 April announcement, the French defence ministry said the DGA had awarded a contract worth EUR600 million (USD642.7 million) to the PA-NG programme's industrial prime contractor MO Porte-Avions (a joint venture of Naval Group and Chantiers de l'Atlantique), and nuclear reactor developer TechnicAtome, covering the provision of long-lead elements related to the ship's nuclear propulsion, namely the K-22 nuclear reactors, their containment structures, and steam generation machinery.

The contract paves the way to start manufacturing these elements, with work expected to continue from 2024 to 2029 in advance of the start of construction of the aircraft carrier, the defence ministry said.


Get the full article by
Already a Janes subscriber? Keep reading


https://www.janes.com/defence-news/france-orders-first-long-lead-items-for-pa-ng-carrier/

The French defence procurement agency (Direction Générale de l'Armement: DGA) has placed the first o...

Request Consultation

Request a free consultation to discover how Janes can provide you with assured, interconnected open-source intelligence.

News Janes | The latest defence and security news from Janes - the trusted source for defence intelligence